These Processes are involved in Preparation of Pipeline Bending & Welding Schedule 
1. Right of Way Preparation
2. Stringing as per Design
3. As-built NGL at C/L at Suitable Distance
4. Prepare NGL Profile
5. Record Pipe Start point of 1st Pipe
6. Record also Pipe Number & Length of Each Pipe
7. Prepare Bending / Welding Plan (Place tie in at Suitable Place as per site Condition)
8. Draw all Pipes with numbering into Profile with different layer
9. Draw polyline for Each Bend as required
10. Export data into Excel
11. Calculate Bend Details from Exported Data (Sag & Over)
12. Place all Bend Data into Profile & Verify
13. Place all Bend Data into Bending Schedule
14. Now you are ready to Prepare Bending Log